How the plan is built

It rests on one rule: prove it on one route or depot before you move the rest. A pilot exposes the problems that only show up with real orders, real drivers and a real day end, while the old way of working still runs everywhere else.

  • Phases overlap. Training starts while set-up is still being tested. The week ranges show that.
  • Each phase has an exit test, written in business terms: a day’s orders run end to end, the day end balances. Not “configuration complete”.
  • The gate between pilot and rollout is a decision, taken by the people who run the operation, against the checklist below.
  • Each phase has one owner by name, not a department.

Getting customers, products and prices ready to move is its own piece of work; our guide to getting distribution data ready to move sets out the sign-offs.

Implementation plan

Implementation plan

Weeks are a starting point. Write your own dates and owners.

Project lead
Pilot route or depot
Start date
Target go-live

Phases

PhaseWeeksWhat happensDone whenOwnerDates
1. Scope and data1 to 2Choose the pilot route or depot. List the processes in scope. Clean customers, products, prices and opening stock. Agree the accounting connection.Pilot scope signed off; data loaded for testing
2. Set-up and test2 to 4Set up routes, price lists, credit terms, devices and documents. Run real orders through order, pick, load, deliver, invoice and accounts.One day of real orders runs end to end with no re-keying
3. Training3 to 4Train office, warehouse and drivers on their own tasks. Drivers run a practice round on the device.Every pilot user has done a full day of their tasks in test
4. Pilot4 to 6Run live on the pilot route or depot. Review issues daily, and check every day end and every invoice posted to the accounts.The go/no-go checklist below is met
5. Fix and decide6 to 8Fix what the pilot found: settings, documents, training. Write the rollout order and the support plan.Go/no-go agreed by the operation’s leads
6. Roll out8 to 12Move the other routes and depots in planned waves, with the pilot team supporting each one.Every site live; the old system read-only

Go/no-go: before moving beyond the pilot

Check YesNo
Orders from every channel in scope reach the warehouse without re-keying
Picks and loads match the orders
Drivers complete the round on the device: delivery proof, returns and payments
Day ends reconcile, or every variance is explained
Invoices and payments reach the accounting package correctly
Users at the next sites are trained
No blocking issue is open

Sign-off

Operations
Finance
Date

Where implementations slip

  • Dirty data found in the pilot. Duplicate customers and wrong prices surface as wrong invoices. Clean before phase 2, not during phase 4.
  • Training too early or too late. Trained three weeks before the pilot, people forget; trained the day before, they panic. Train in the fortnight before.
  • A pilot nobody can fail. If the go/no-go is a formality, problems move to every depot at once.
  • The old process left open. Keep it as a fallback for real failures in the pilot, and watch how often it gets used. If people reach for it out of habit, the training needs another pass.